Park renovation moving ahead despite vandalism

Despite recent setbacks construction at Dolores Park is moving ahead.
Important highlights include:

  • The North Restroom is 99% complete. New toilets, sinks, and hand dryers have all been installed.
  • The clubhouse will start demolition on Monday, and will last about 1 month.  The construction fences have shifted in order to include a safe and secure perimeter around the building during this demolition.
  • Operations Building is complete and the Rec & Park team is moving in.
  • Final stretches of pathways will be paved in the next one to two weeks.
  • Site lighting is almost complete, and site signs and furnishings will be installed shortly.

Sitework-Path-between-Multi-Use-Basketball-Courts-and-Tennis-Court-2015.02.26-Measure-for-Railing-1000x750

The vandalism on Valentines weekend caused about $100,000 in damage and will likely delay the reopening of the north side of the park.  The majority of the damage was incurred when the vandals hot-wired the construction equipment and drove across the newly installed turf and concrete, damaging the equipment, the new grass lawn, and portions of newly-placed concrete that hadn’t fully cured.  The vandals broke portions of the irrigation system, crashed into building and site walls, and started a fire in the new maintenance yard.  Two arrests were made by the SF Police Department. The contractor is still assessing the damage and the ramifications to the project’s schedule.